THE MOMBASA – NAIROBI PIPELINE This pipeline system was commissioned in February 1978 and consists of 450km 14-inch diameter pipeline, eight pump stations and a flow rate of over 830,000 litres per hour. Line V the new 20-inch Mombasa – Nairobi pipeline was completed in 2018 and is expected to meet demand for petroleum products for Kenya and the region until the year 2044. The flow rates to Nairobi for the new line will be about 1.9 million liters per hour by 2023 and 2.6 million liters per hour by 2044.